SCS Energy: Outer Loop LFG to Pipeline RNG Plant

Outer Loop RNG Project – Confidential Client

LFG to Pipeline RNG PlantSCS, responsible for the design of this 5,000 scfm inlet capacity LFG-to-pipeline RNG plant which began commercial operation in March 2018. The product gas capacity is 3,300 MMBtu/day. The plant employs these technologies:

  • Darco for H2S removal;
  • LFG refrigeration;
  • LFG compression with flooded-screw compression;
  • Membranes for CO2 removal;
  • PSA for N2 removal;
  • TOX; and
  • Product gas compressor (700 psig).