Client & Employee Access Search About Us Contact Us Sitemap ![]() ![]() ![]() ![]() ![]() |
||
![]() |
SCS Energy Operation/Maintenance Projects |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
• Services SCS Energy provides ongoing operation/maintenance services for most of the power plants that SCS Energy has installed. SCS Energy also provides ongoing operation/maintenance services for power plants that were installed by other firms. As of July 2006, SCS had operation/maintenance responsibility for nine power plants having a total capacity of 16 MW. Two other projects totaling 6.4 MW are under contract and are scheduled to begin operation in late 2006. Several current and prior operation/maintenance projects are listed below:
_______________________________________________________
Project Background The project operates in parallel with Southern California Edison (SCE), and is base loaded and load-following. It displaces power purchases from SCE. SCS was responsible for the following aspects of the project:
The total plant capacity is 2.0 MW. SCS currently has responsibility for operation/maintenance of this facility. SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The project originally employed one natural gas fired Caterpillar reciprocating engine with a total installed capacity of 1.6 MW. The project supplies electricity, steam and chilled water to the Alta Dena Dairy. The project employs post-combustion, selective catalytic reduction (SCR) for NOx control, and has a CEMS. The project operates in parallel with Southern California Edison Company (SCE), is base loaded, and displaces power purchases from SCE. The project began commercial operation in September 2004. SCS was responsible for start-up and day-to-day operation/maintenance for this facility for its first six months of operation. SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The Pennsauken LFGTE facility employs three Caterpillar 3516 engine/generators. The plant has a capacity of 2.8 MW. The project began operation in November 2004. The facility generates power for "over-the-fence" sale to a manufacturer of aluminum shapes. The power purchaser remains interconnected to the local electric utility for the purpose of obtaining standby and supplemental power and for export of excess power to the regional power grid. SCS’ responsibilities on this project include:
The plant has a capacity of 2.8 MW. SCS performed this work on a turnkey basis. SCS had operation/maintenance responsibility for this facility for its first fifteen months of operation. SCS Responsibilities (marked with "X")
return to page top _________________________________________________ Project Background Problems with the microturbine plant's fuel pretreatment, fuel compression and hot water recovery equipment led to a suspension of plant operation in 2001. SCS was engaged to completely upgrade and refurbish the plant including:
SCS undertook this project on a turnkey basis. Its total capacity after refurbishment was 390 kW. The refurbished plant commenced operation in November 2003. SCS currently has operation/maintenance responsibility for this facility. SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The project employs two 250 kW FuelCell Energy, Inc. fuel cells. The fuel cells use digester gas as a fuel. The methane content of the digester gas is 62 percent. The project began operation in November 2004. The project incorporates a waste heat hot water generator and an SCS designed/fabricated digester gas pressurization/treatment skid. The skid removes moisture, particulates, hydrogen sulfide, halogenated compounds and siloxanes. The hot water is used to heat the WWTP's anaerobic digesters, which frees up additional digester gas for power generation. The entire power plant, including digester gas supply and hot water interfaces, are under the control of an SCS designed/fabricated SCADA system. The power plant operates in parallel with Southern California Edison (SCE) as a baseload unit. The power plant displaces power otherwise bought from SCE at retail rates. The project qualifies for net metering under CaPUC regulations. The total power plant capacity is 500 kW. SCS executed the project on a design/construct basis. The project is the largest digester gas fueled fuel cell project in California. SCS currently has operation/maintenance responsibility for this facility. SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The project employs ten Capstone 30 kW microturbines and one 250 kW Ingersoll-Rand microturbine, all fired on landfill gas with a methane content as low as 38 percent. The project commenced operation in April 2005. A project incorporating the ten Capstone microturbines originally commenced operation at this location in July 2001. After less than a year of operation, the project was shut down due to operational problems with the landfill gas conditioning equipment and the microturbines themselves. SCS’s responsibilities on this new project included:
The project exports 85 percent of the power it produces to the municipally-owned power distribution system. The project contributes to the City’s commitment to increase green power production. The total capacity of this plant is 550 kW. SCS executed the project on a turnkey basis. SCS currently has operation/maintenance responsibility for this facility.SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The project employs four Cooper reciprocating engines with a total installed capacity of 7.5 MW. The project is landfill gas fired and has the capability of co-firing with natural gas during periods of low landfill gas methane content. The project sells power to the Los Angeles Department of Water and Power (LADWP). In addition to full responsibility for plant operation/maintenance, SCS implemented a $2.4 million plant betterment project to reduce NOx emissions, and to increase plant availability and capacity factor. Key elements of the betterment program included replacement of the individual engine control systems, installation of a plant-wide SCADA system, and installation of continuous emissions monitoring systems (CEMS) on each engine. In the first year of operation, SCS self-performed major overhauls of two of the engines, including an engine which had been abandoned in-place by the prior owner of the power plant. SCS has been responsible for operation and maintenance of this facility since February 2005. SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The project employs two Cooper Superior reciprocating engines with a total installed capacity of 3.8 MW. The plant was recently updated with a new engine control system and a continuous emissions monitoring system to improve air emissions compliance. The plant currently sells power to Southern California Edison Company. SCS has a contract to provide full operation/maintenance services at this site. SCS is also responsible for scheduling of power sales.SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The project is the largest project in the United States that produces pipeline quality gas from natural gas using pressure swing absorption (PSA) technology. The inlet capacity is 9.0 mmscfd. Principal components of the plant are as follows:
SCS has been responsible for operation/maintenance of this facility since June 2005. SCS Responsibilities (marked with "X")
return to page top _________________________________________________
Project Background The Mountaingate Gas Plant cleans and compresses 2.0 mmscfd (1,400 scfm) of landfill gas. The processed gas is delivered to the University of California at Los Angeles (UCLA) via a 5.5 mile pipeline where it is co-fired with natural gas at UCLA’s 40 MW on-campus cogeneration plant. The gas plant consists of the following major components:
The gas plant is located adjacent to the Mountaingate Country Club. SCS is responsible for the operation/maintenance of the gas plant and the pipeline, environmental permitting and reporting, liaison with the Mountaingate Country Club, and coordination of day-to-day operation with the UCLA cogeneration plant. SCS Responsibilities (marked with "X")
|