design capacity report

May 21, 2021

landfill emissions

(40 CFR Part 60, Subpart OOO)

On May 21, 2021, EPA published the final MSW Landfills Federal Plan, which implements the 2016 Emission Guidelines (EG Subpart Cf) under 40 CFR Part 62 Subpart OOO.  The Federal Plan becomes effective June 21, 2021, and impacts landfills that have not triggered NSPS Subpart XXX requirements and landfills located in states and Indian country without EPA-approved EG Cf rules.

Affected are MSW landfills that commenced construction on or before July 17, 2014, and have not been modified or reconstructed since July 17, 2014.

The Federal Plan requires existing landfills that reach an annual emissions threshold of 34 metric tons of nonmethane organic compounds (NMOC) or more to install a system to collect and control landfill gas (GCCS).  It also implements various emission limits, compliance schedules, testing, monitoring, reporting and recordkeeping requirements for GCCSs established in the 2016 Emission Guidelines for MSW Landfills.

The Federal Plan also establishes a definition for “legacy controlled landfills.”  These are landfills that have previously satisfied the requirement to submit an initial design capacity report, initial (or annual) NMOC emission rate reports, and collection and control system design plan under 40 CFR part 60, subpart WWW; 40 CFR part 62, subpart GGG; or a state/tribal plan implementing 40 CFR part 60, subpart Cc.

If you are subject to the Federal Plan and are not a “legacy controlled landfill,” you must submit a design capacity report by September 20, 2021.  And if the design capacity report indicates a capacity equal to or greater than 2.5 million Mg and 2.5 million m3 of solid waste, you must also submit an initial NMOC emission rate report within 90 days after the effective date of the Federal Plan (September 20, 2021).

SCS is working to develop a Technical Bulletin for distribution to our mailing list and on social media. The Bulletin will consolidate the Final Rule into several pages highlighting significant dates and key impacts for you.

 

 

 

 

 

 

Posted by Diane Samuels at 3:17 pm

May 14, 2021

SCS Engineers periodically prepares Technical Bulletins to highlight items of interest to our clients who have signed up to receive them. We also publish these on our website and social media accounts as well.

 

(40 CFR Part 60, Subpart OOO)

EPA is submitting a pre-publication copy of the final MSW Landfills Federal Plan to implement the Emission Guidelines (EG) and Compliance Times issued on May 10, 2021. The Final Plan becomes effective 30 days after publication in the Federal Register, impacting any remaining landfills without approved EG Cf rules.

EPA’s federal plan includes an inventory of designated facilities and an estimate of emissions from those designated facilities. The Agency estimates 1,590 landfills will potentially be covered in 42 states and the US territories of Puerto Rico and the Virgin Islands, and one tribal entity.

SCS Engineers is preparing a Technical Bulletin for distribution to our mailing list and on social media. The Bulletin will consolidate 133 pages into several pages highlighting significant dates and impacts for you.

 

EPA Actions: Final Federal Plan Requirements for Municipal Solid Waste Landfills

 

Affected are MSW landfills that commenced construction on or before July 17, 2014, and have not been modified or reconstructed since July 17, 2014.

EPA is implementing emission guideline requirements for existing MSW landfills located in states and Indian country where state plans or tribal plans are not currently in effect because they were not submitted or approved.

 

The Final 2016 Emission Guidelines for MSW Landfills require existing landfills that reach a landfill gas emissions threshold of 34 metric tons of nonmethane organic compounds (NMOC) or more per year to install a system to collect and control landfill gas (GCCS).

It also implements the emission limits, compliance schedules, testing, monitoring, reporting and recordkeeping requirements established in the Emission Guidelines for MSW Landfills.

Unless the landfill is a legacy controlled landfill, owners or operators of MSW landfills subject to the MSW Landfills Federal Plan must submit a design capacity report within 90 days after the effective date of the Federal plan (40 CFR 62.16724(a)).

Should the design capacity report indicate a capacity equal to or greater than 2.5 million Mg and 2.5 million m3 of solid waste a landfill can accept; then, an annual NMOC emission rate report must also be submitted within 90 days after the effective date of the Federal plan, and then every 12 months until the landfill installs a GCCS (40 CFR 62.16724(c)).

You may find a copy here on EPA’s website.

 

Contact your SCS project manager or for assistance. Follow us on Twitter, LinkedIn, or Facebook to receive EPA alerts and SCS Technical Bulletins, along with other news.

 

 

 

Posted by Diane Samuels at 6:00 am